Construction Updates

Now more than ever, the world needs creative thinkers, courageous leaders and dynamic innovators. At St. Catherine's we have a bold vision to develop the southern third of campus into a catalyst for transformational experiences that will engage the hearts and minds of every student and the broader Richmond community.

Project Timing
Phase 1: 
•Performance Park, Julie Dayton Field and South Parking Lot began construction Spring 2018; project concluded Spring 2019


Phase 2:
• McVey Hall closed May 2019; demolition completed Summer 2019
• Maple Avenue Studio completed Fall 2019
• Permits submitted Fall 2019
• Current goal to break ground by Summer 2020 (dependent upon meeting the guideline of 75% of project cost funding secured)

Recent News

List of 8 news stories.

Archive

Questions?

List of 2 members.

Field preparations

If you would like to receive construction updates, please contact construction@st.catherines.org.